Our rental season has begun and we are blessed to be able to report very positive feedback. Our guest are having great times with their families and enjoying the beach…we couldn’t be more pleased. We also want to thank our guest for choosing La Dolce Vita…we know there are many choices. Dale & Mary Jo

Learn more »

Happy Easter!

Life is good at the beach

We have spent the last two weeks here at our beach home. Much progress has been made, all furniture is in, TVs and WiFi are setup and wired. With the exception of a few finishing touches, we are ready to welcome our first guests. Our son in law has updated the pictures and the website, […]

Learn more »

2/17/13 update on house progress.

We are happy to report that the Beach House is complete. We had the final inspection last week and all went well. We will be updating pictures this week. We couldn’t be more pleased with the results. The kitchen is fabulous, the views from inside the family Rooms are stunning and we think the children […]

Learn more »

Another update!

Good news from our builder this week.  Countertop, carpet and appliances are all in.  He is scheduling the inspection for next week.  Hopefully everything will pass and we will have the green light to come own to do the final walk thru.  We are anxious to get more pictures out and start furnishing the beach […]

Learn more »

January 27,2013 Update

Builder informed us Friday that plumbing is all in as well as electrical and some of the appliances have been installed.  Looks like all that is left to finish is the counter top and the carpet.  Counter top taking longer than expected.  Should be finished in next 2 weeks.  We also did some shopping this […]

Learn more »

Beautiful Weather In January

outdoor5

We spent the last 4 days at our beach house.  Weather was beautiful 70 degrees, very unusual for this time of year.  The house is coming along.  The bunk beds are built.  Bathroom vanities are installed.  Our builder is projecting to have La Dolce Vita complete in 2-3 weeks.

Learn more »

Construction Update – 1/10/13

Construction is coming along quite well and on schedule. Exterior is complete now, and interior is coming along quite nicely. The new tile floors are in, walls are painted, kitchen cabinets are in, and the light fixtures are going in. We will be updating with plenty of pictures this weekend. We are excited and hope […]

Learn more »